A developer has exchanged on an infill townhouse site, but the bank has taken six weeks to issue conditional terms and still wants stronger pre-sales. This developer funding example shows how a private funding structure can keep a viable project moving when timing, valuation policy or bank credit appetite becomes the constraint.

The figures below are illustrative, but the scenario is familiar across metropolitan and regional Australia. It involves a small residential development with a solid end value, an experienced borrower and enough property equity to support a practical capital stack.

Developer funding example: six-townhouse project

A company controlled by an experienced developer has contracted to purchase a site for $2.20 million. The plan is to demolish the existing dwelling and construct six townhouses. The developer has obtained planning approval, fixed-price building documentation and an as-if-complete valuation supporting a gross realisation value of $7.40 million.

The challenge is settlement. The developer needs certainty within 21 days and has only one townhouse pre-sold. A major bank is prepared to consider the deal, but requires three pre-sales, updated builder due diligence and a longer credit process. Waiting may mean losing the site and the deposit.

The anticipated total development cost is $5.20 million:

  • Site acquisition and stamp duty: $2.34 million
  • Demolition, construction and external works: $2.25 million
  • Professional fees, council charges and head works: $280,000
  • Interest, selling costs and contingency: $330,000

The developer contributes $1.25 million in cash and equity. The remaining $3.95 million is structured through a senior private construction facility and a smaller mezzanine facility.

The senior construction facility

A private lender provides a first-mortgage facility of $3.30 million. The facility is secured against the development site and advanced progressively, rather than paid as one lump sum. It covers the land settlement, approved construction draws and part of the interest reserve.

The lender assesses the transaction against both total development cost and the projected end value. At a $3.30 million limit, the senior debt is about 63 per cent of total project cost and 45 per cent of gross realisation value. Those ratios provide meaningful lender protection while giving the developer enough funding to acquire the site and start works.

The lender may require quantity surveyor reports before construction draws are released. This helps confirm that completed works match the claimed stage and that enough undrawn funds remain to finish the project. It can add administration, but it protects both parties from a half-built site with a funding shortfall.

The mezzanine component

The remaining $650,000 is provided as mezzanine finance. It sits behind the first mortgage lender and is commonly secured by a second mortgage, caveat or other agreed security position. The mezzanine lender accepts more risk because it is repaid after the senior lender, so pricing will generally be higher.

Here, mezzanine funding fills the gap between the senior lender’s maximum exposure and the developer’s available equity. It means the borrower does not need to sell another investment property or bring in an equity partner for a relatively modest shortfall.

That flexibility has a cost. Mezzanine finance can materially reduce project profit if held for too long. It works best where the project has a clear build programme, credible contingency and a realistic exit. It is not a substitute for adequate developer equity or an underfunded construction budget.

How the money moves through the project

At settlement, the senior lender advances enough to complete the purchase and meet associated acquisition costs. The developer contributes its agreed cash contribution first or alongside the lender funds, depending on the facility terms. Mezzanine funding may be available at settlement or retained for later construction stages once the senior lender’s conditions are met.

During construction, the builder submits progress claims. The developer provides invoices, progress certificates and quantity surveyor evidence where required. The senior lender releases approved drawdowns for completed work. If the project remains on programme and within budget, the funding continues through to practical completion.

This process is more controlled than an ordinary business loan, but for good reason. Development finance is tied to an asset that changes in value and condition throughout construction. The lender wants visibility over whether the project can still be completed and sold if market conditions soften.

A sensible facility also includes an interest reserve. Rather than requiring monthly interest to be paid from operating cash flow, the lender may retain a portion of the approved limit to service interest during the build. This can protect working capital, particularly where the developer is running several projects or a separate trading business.

The exit strategy matters as much as the approval

For this example, the primary exit is the sale of all six townhouses on completion. With a gross realisation value of $7.40 million, selling costs and GST must be factored into the cash flow before estimating profit. A valuation is not a guarantee of sale price, so the developer should also allow for slower sales, buyer finance issues and possible incentives.

The secondary exit is retained stock finance. If market conditions are soft at practical completion, the developer may retain two completed townhouses and refinance the construction debt into a longer-term first-mortgage facility. The remaining stock can then be sold without accepting rushed offers simply to meet a development facility expiry date.

This alternative is particularly valuable where the location is sound and there is a credible leasing or sales strategy. It does, however, depend on completed titles, valuation evidence, borrower serviceability or rental coverage, and the refinance lender’s policy at that time. An exit should be planned before settlement, not invented in the final month of construction.

What could change the funding structure?

Not every developer needs mezzanine finance. If the borrower has more cash, another unencumbered property or stronger pre-sales, a senior lender may provide sufficient leverage on its own. Conversely, a first-time developer, a complex build or a project with limited contingency may require more equity and a lower loan-to-cost ratio.

The lender will also look beyond the spreadsheet. Key considerations include the builder’s licence and track record, the developer’s experience with comparable projects, planning status, contract price, valuation methodology, projected sales rates and the quality of the security. Credit history can matter, but private lenders often place greater weight on the underlying property, the project feasibility and the exit pathway than a mainstream bank would.

Where settlement is urgent, a short-term caveat loan or bridging facility may sometimes secure the site first, followed by a refinance into construction funding once full reports are complete. That approach can solve a timing problem, but it creates another refinance event and additional cost. It needs a clear path to the larger facility, not just optimism that one will appear later.

Documents that support a faster decision

A lender can assess a development opportunity more efficiently when the borrower presents a complete package. In practice, that means the contract of sale, rates notice, plans and permits, construction contract, feasibility, valuation where available, builder details, entity structure and evidence of the equity contribution.

If pre-sales exist, provide signed contracts and deposit details. If there are no pre-sales, the borrower should explain why the project remains viable without them, using local comparable sales, realistic absorption assumptions and a conservative contingency. Clear information does not guarantee approval, but it gives a lender confidence that the developer understands the numbers.

For borrowers facing a bank delay, a private funding solution can provide the certainty needed to secure a site, finish a build or release equity from an existing asset. The right structure is the one that funds the project without placing unnecessary pressure on the exit, so test the downside figures early and seek competitive terms before the settlement clock becomes the main decision-maker.